What does “Effort driven” option do?
What does “Effort driven” option do?You may wonder what does “Effort driven” option in Task Detail Form do?Here I have 2 tasks.Task A doesn’t have Effort driven check. When I assign 2 resources … [Read more...] about What does “Effort driven” option do?
How does “Resource curve” work?
How does “Resource curve” work?Let say we have an activity with 100 days duration and 100 labor units. By default it use Linear spread.It mean, when you reach 5% of duration (5th day in this example) … [Read more...] about How does “Resource curve” work?
How does “Actual units” spread when you use Resource curve
How does “Actual units” spread when you use Resource curveWe have an activity which is applied “Back Loaded” resource curve.When we update progress, the Actual unit will spread just like we plan. … [Read more...] about How does “Actual units” spread when you use Resource curve