Turn off Auto Compute Actuals for 1 activityBy default our project check this option like below image so that when you update Duration % complete, P6 will update Actual units for you.When you … [Read more...] about Turn off Auto Compute Actuals for 1 activity
Primevera P6
Does Resource Curve affect Remaining Late Unit
Does Resource Curve affect Remaining Late UnitThe Resource curve obviously affect Remaining Early Unit. How about Remaining Late Unit. The answer is YES.We have a resource assignment window … [Read more...] about Does Resource Curve affect Remaining Late Unit
Shortcut for moving WBS element
Shortcut for moving WBS element In WBS window, we can create a whole WBS structure by keyboard (faster than using mouse).In stead of click on the Plus icon to create a new WBS, we can press “Insert” … [Read more...] about Shortcut for moving WBS element
Can not import Layout
Can not import Layout Your colleague send you Primavera XER file and Layout file. After you import project successfully, you click on Layout -> Open -> Import -> Select the layout. And this … [Read more...] about Can not import Layout
Open Microsoft Project file and a blank screen appear
Open Microsoft Project file and a blank screen appearWhen you work with Microsoft Project 2010 in 2 monitor, you finish working, save the file and then next day you open a project file and a blank … [Read more...] about Open Microsoft Project file and a blank screen appear
Remove relationship for multiple activities
Remove relationship for multiple activitiesYou have a group of activities which need to be removed all relationshipInstead of going to each activity and click the Remove button, you can select … [Read more...] about Remove relationship for multiple activities
How does “Actual units” spread when you use Resource curve
How does “Actual units” spread when you use Resource curveWe have an activity which is applied “Back Loaded” resource curve.When we update progress, the Actual unit will spread just like we plan. … [Read more...] about How does “Actual units” spread when you use Resource curve
Primavera P6 Training: Applying Filters to a Project
Primavera P6 Training - FilteringFiltering is a quick and easy way to determine which activities are displayed in a layout. Filtering enables you to create customized layouts that:Limit the number of … [Read more...] about Primavera P6 Training: Applying Filters to a Project
Primavera Contract Manager is your projects solution.
Primavera Contract ManagerStaying in control of your projects agenda, deliverables, and budget is critical to the forthcoming of your business and the upcoming success of your project. Keepin on … [Read more...] about Primavera Contract Manager is your projects solution.
Primavera Training- Using Resource Lag & Resource Duration
Primavera P6 Training Managing your Resources and Staff with Primavera P6With the economy the way it is at the moment, many of us find ourselves taking advantage of the opportunities to be Mr. or … [Read more...] about Primavera Training- Using Resource Lag & Resource Duration