Create critical path for “any activity”In Primavera when we use the default “Critical” filter, it will show the critical path for the whole project (for the last activity).How about if we want … [Read more...] about Create critical path for “any activity”
Blogs
Microsoft Project : Custom View (New view) appear in all Project
Microsoft Project : Custom View (New view) appear in all Project When you need to customize a View and save it for later use, sometimes we only need that View for a certain Project.However by … [Read more...] about Microsoft Project : Custom View (New view) appear in all Project
What does “Effort driven” option do?
What does “Effort driven” option do?You may wonder what does “Effort driven” option in Task Detail Form do?Here I have 2 tasks.Task A doesn’t have Effort driven check. When I assign 2 resources … [Read more...] about What does “Effort driven” option do?
How does “Resource curve” work?
How does “Resource curve” work?Let say we have an activity with 100 days duration and 100 labor units. By default it use Linear spread.It mean, when you reach 5% of duration (5th day in this example) … [Read more...] about How does “Resource curve” work?
How does “Actual units” spread when you use Resource curve
How does “Actual units” spread when you use Resource curveWe have an activity which is applied “Back Loaded” resource curve.When we update progress, the Actual unit will spread just like we plan. … [Read more...] about How does “Actual units” spread when you use Resource curve
Primavera P6 Training: Applying Filters to a Project
Primavera P6 Training - FilteringFiltering is a quick and easy way to determine which activities are displayed in a layout. Filtering enables you to create customized layouts that:Limit the number of … [Read more...] about Primavera P6 Training: Applying Filters to a Project
Primavera Contract Manager is your projects solution.
Primavera Contract ManagerStaying in control of your projects agenda, deliverables, and budget is critical to the forthcoming of your business and the upcoming success of your project. Keepin on … [Read more...] about Primavera Contract Manager is your projects solution.
Primavera Training- Using Resource Lag & Resource Duration
Primavera P6 Training Managing your Resources and Staff with Primavera P6With the economy the way it is at the moment, many of us find ourselves taking advantage of the opportunities to be Mr. or … [Read more...] about Primavera Training- Using Resource Lag & Resource Duration
Primavera P6 Training : Utilizing Thresholds in Primavera P6
Primavera P6 TrainingWhat are thresholds in Primavera P6? A threshold is a user-defined trigger that identifies when the status of an activity has exeeded or is close to moving beyond an acceptable … [Read more...] about Primavera P6 Training : Utilizing Thresholds in Primavera P6
Primavera P6 Training : Resource Assignments Window
PRIMAVERA P6 TRAININGWelcome back to our Primavera P6 training blog! Today we are going to cover the resource assignments window in Primavera P6.The Resource Assignments window allows you to view and … [Read more...] about Primavera P6 Training : Resource Assignments Window